Road works for the project "Making a track on the sole -480m in the mine" 10th anniversary of Kazakhstan's independence "
Donskoy GOK - branch of AO TNK Kazchrome "wants
Realized. In order to develop a new mining field, it is necessary to establish a connecting line between the shaft and the weather shaft of the mine. In addition to the actual route access, the production is different
Cross sections and route crossings are part of the order. In the most difficult geology, more than 3,000 m of the connecting line with a cross section of the route
13.5 m2. Most of the previous tunneling was carried out in a serpentinite, the fields of which are covered with talc
Water caused an extremely brown mountain range. Constantly changing mountain conditions and initial difficulties with ordering
Services provided by the contracting authority in the implementation of a continuous
The drive is the greatest difficulty. However, it has been shown that with the chosen technology of a mechanized drive (2-arm drilling machine AtlasCopco
Rocket boomer 282, tunnel and loader excavator ITC TEREX-SCHAEFF 120
F4 and shotcrete technology MEYCO Oruga combined with a cleaning master
Concrete pump) becomes a high quality and durable structure
can be used. The route is made by drilling and blasting,
the results of the "New Austrian Tunneling"
second hand. After the explosion, the first fuse is reinforced with a steel fiber
wet shotcrete. The final expansion with concrete takes place
in installation thicknesses between 5 and 20 cm. These depend on the
geological conditions. The final extension of the route will be
Completed after removing the head. Mountain anchors are installed in addition to the shotcrete to minimize convergence. As a result, the convergences that have so far occurred in the heavily broken and irregular mountains
In contrast to the track areas, which were previously with the
of the customer, negligibly small. The distance-related removal of the accumulated onslaught and the transport of equipment,
and device was restored so that a reliable supply to the drive point
Guaranteed. At the same time despite difficult purchasing conditions and
poor quality characteristics, supply of materials from local suppliers
established. A further substitution of German deliveries with local solutions is currently being examined. Problems arise again and again, the disproportionately high coordination effort of the processes and
both on the technical side and in planning and billing.
The differences in mentality, culture and basic economic system do not make everyday project work easier.